Close Menu
    Facebook X (Twitter) Instagram
    Trending
    • ⚡ Cable Types in Distribution: XLPE vs PILC vs Aerial Bundled Cables
    • ⚡ Smart Grid in Distribution: Role, Challenges & Indian Scenario
    • ⚡ Power Factor Correction in Distribution Systems
    • ⚡ Understanding Distribution Protection: Fuses, Relays & Reclosers
    • ⚡ Voltage Drop in Distribution Lines: Causes, Calculation & Correction
    • 🛠️ Distribution Transformer Maintenance: Checklist and Tips
    • INTRODUCTION TO SUBSTATION EARTHING
    • Maintenance of GIS (Gas-Insulated Switchgear)
    Electric Know How
    • Home
    • Generation
      • Hydropower Station
      • Thermal Power Station
      • DISTRIBUTED ENERGY SOURCES
      • Diesel Generator
      • Industrial Tools
      • DC System-Generating Stations
    • Transmission
      • High Voltage DC Transmission
      • High Voltage AC Transmission
        • Transmission line – An Overview
        • TRANSMISSION TOWER CONFIGURATION
        • Transmission Towers-Key Features
    • Distribution
      • ⚡ Understanding Electrical Distribution Systems: Basics to Architecture
      • ⚡ Top 5 Faults in Distribution Lines and How to Fix Them
      • 🛠️ Distribution Transformer Maintenance: Checklist and Tips
    • Protection
      • Power System Protection
        • Types of Fault in Power System
        • Relay Setting Calculation for Substation
        • Circuit Breaker
          • Nameplate details of SF6 Circuit Breaker
          • Major parameters of a circuit breaker
          • What is the use of an anti-pumping relay?
          • What is an IR Value Test in a Circuit Breaker? An overview
          • Testing of Circuit Breaker
        • Key Components of Control & Relay Panel
          • Relay Setting Calculation for Substation
          • Trip Circuit Supervision Relay
          • Three Phase Control Wiring
        • Switching Surges and Its Remedies
      • OVERVIEW OF TRANSFORMER PROTECTION
        • Differential Protection of Transformer
      • OVERVIEW OF GENERATOR PROTECTION
      • Distance Protection
      • Electrical Safety
    • Switchgear
      • Electrical Sub-Station
        • BATTERY SYSTEM IN GRID SUBSTATION
        • Operation of Float Cum Boost Charger
        • Protection Circuitry of Battery Charger
        • Power Transformer
          • INSULATION RESISTANCE OF TRANSFORMER
          • WTI AND OTI in Power Transformer
          • Transformer Oil Dielectric strength
          • On Load Tap Changing of Transformer
          • TRANSFORMER MAINTENANCE
        • Sub-Station Operation
        • Multiplying Factor for Energy Meter
      • Current Transformer
        • Nameplate Detail of Current Transformer – A Detail Guide
        • Current Transformer Knee Point Test – A Detailed Overview
        • What is a Current Transformer Polarity Test- Detailed Guide
        • Ratio test of Current Transformer
      • Potential Transformer
      • Isolator in Substation
        • Nameplate Detail of Isolators/Dis-connectors- A Detail Guide
      • Electrical Busbar
      • Insulators
      • Clamps and Connectors
      • Fire Fighting System
      • Lightening Arrester
        • LCM Test of a Lightning Arrestor – An Overview
      • Gas Insulated Substation
        • Local Control Cubicle
        • SF6 circuit breaker gas compartment
        • Maintenance of GIS (Gas-Insulated Switchgear)
    • Q&A
      • FAQS ON Current Transformer
      • POWER SYSTEM
      • FAQ ON BUSBAR
    Electric Know How
    Home»Switchgear»Ratio test of Current Transformer
    Switchgear

    Ratio test of Current Transformer

    madhusmitaBy madhusmita23 November 2023Updated:31 January 2024No Comments4 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Share
    Facebook Twitter LinkedIn Pinterest Email

    The ratio test of a current transformer (CT) is a crucial step in ensuring its accuracy and reliability in measuring current in a power system. Below is a general procedure for performing the ratio test on a current transformer located in Switchyard.

    Table of Contents

    Toggle
    • Safety Precautions:
    • Equipment Required:
    • Procedure:
    • Summary

    Safety Precautions:

    Before starting the ratio test, it is essential to follow proper safety precautions. Ensure that the equipment is de-energized and properly isolated. Use appropriate personal protective equipment (PPE), and follow safety procedures to prevent accidents.

    Equipment Required:

    1. CT Test Set
    2. Multi-ratio CT Test Switch Box
    3. CT Analyzer
    4. Secondary Injection Test Set
    5. Current and voltage sources
    6. Multimeter
    7. Wiring and connection accessories

    Procedure:

    Prepare the CT:

    • Ensure that the CT is isolated from the power system.
    • Verify that the CT is properly grounded.
    • Inspect the CT for any visible damage or defects.
    • Isolate CT:
    • Physically isolate the CT from the power system to prevent any flow of current during the test.
    • Check Connections:
    • Verify that all connections are correct based on the CT’s primary and secondary ratings.
    • Ensure proper polarization of the CT.
    • Using the basic required components in the test, we will make the following connections and main procedure to conduct the ratio test:
    • VARIAC output will go into the input of step up-current transformer.
    • Then CT(another) output will go in the primary P1 of our main CT on which we are conducting the ratio test.
    • The current that is coming out of P2 is injected in the CT (another) to make a current path.
    • Current will enter from P1 and leave from P2.
    • Now we will take output from the secondary terminal box.
    • We can test on any of the 3 cores available in the secondary box. Then output will be from terminal 1 to terminal 2 or terminal 1 to terminal 3.    
    • For 1S1 and 1S2, we will short both of them, to get output from them.
    • After shorting both terminals, we added a clip-on meter on primary and secondary take readings.
    • By turning the knob of VARIAC, we can get the output current to inject in CT (another) input.
    • VARIAC needs 220/240V of AC to start and to provide the output.
    • We will set the primary to 30A b setting the value from VARIAC. Eventually the secondary will give us the 0.1A current. This is what we were looking for to test the terminal of 1S1 and 1S2. This ratio must be verified to check the beneficial results.
    • Now if we check the ratio of 1S1 and 1S2, then by turning the knob of VARIAC. It will provide 30A in primary and 0.051A in secondary. As we know there is a 600 ratio, between the 1S1 and 1S2, so we achieve the 0.1A in secondary.
    • Now if we check the ratio between the 1S1 and 1S3, we will get 0.1A in secondary by getting the 60A in primary from the clipboard.
    • All output values will be shown on a clip-on meter and you should note those values.
    Sr. No.P1  &P2 CurrentSecondary ConnectionsSecondary CurrentOutput result
    1301S1 TO 1S20.1Good
    2601S1 TO 1S30.112Good
    3302S1 TO 2S20.1Good
    4602S1 TO 2S30.104Good
    5303S1 TO 2S20.1Good
    6603S1 TO 2S30.1Good
    format for record

    Reconnect CT:

    • After completing the test and ensuring that the CT is in good working condition, reconnect it to the power system.

    Summary

    We have studied the key components and procedures for conducting the ratio test using these elements. This test is conducted to ensure the reliability of the Current Transformer in our power system for its proper working.

    Always follow the manufacturer’s instructions and industry standards when performing ratio tests on current transformers. It’s also recommended to consult with experienced personnel or hire professional testing services for critical equipment to ensure accuracy and safety.

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleCurrent Transformer IR Test – A Detailed Guide
    Next Article What is a Current Transformer Polarity Test- Detailed Guide
    madhusmita
    • Website
    • Facebook
    • Instagram
    • LinkedIn

    Related Posts

    ⚡ Smart Grid in Distribution: Role, Challenges & Indian Scenario

    16 May 2025

    ⚡ Power Factor Correction in Distribution Systems

    16 May 2025

    ⚡ Voltage Drop in Distribution Lines: Causes, Calculation & Correction

    16 May 2025

    Comments are closed.

    Archives
    Categories
    • Distribution (15)
    • Generation (10)
    • Protection (24)
    • Q&A (7)
    • Switchgear (48)
      • Nameplate Details (2)
    • testing (11)
    • Transmission (20)
    Recent Posts
    • ⚡ Cable Types in Distribution: XLPE vs PILC vs Aerial Bundled Cables
    • ⚡ Smart Grid in Distribution: Role, Challenges & Indian Scenario
    • ⚡ Power Factor Correction in Distribution Systems
    • ⚡ Understanding Distribution Protection: Fuses, Relays & Reclosers
    • ⚡ Voltage Drop in Distribution Lines: Causes, Calculation & Correction
    Certification Course
    Electric Volt

    Quick Links

    • Home
    • About Us
    • Contact Us

    Post Categories

    • Generation
    • Transmission
    • Distribution
    • Protection
    • Switchgear
    • Q&A

    Vip Link

    • Privacy Policy
    • Disclaimer
    • Terms and Conditions

    Contact Us

    • ele.mamohanty@optcl.co.in
    Linkedin